Bloxwich
Bloxwich is a storage project of 41 MW in NESO's TEC Register of 23 Oct 2026, connecting at Bustleholm 132kV Substation (NGET). Status: Built.
- Customer
- BLOXWICH ENERGY STORAGE LIMITED
- Connection site
- Bustleholm 132kV Substation
- Transmission owner
- NGET
- Technology
- Storage
- Capacity (TEC)
- 41 MW
- Agreement
- Embedded
- Status
- Built
- NESO project number
- PRO-001243
Also at Bustleholm 132kV Substation
| Project | Technology | MW |
|---|---|---|
| Bustleholme | Storage | 57 |
Source
- NESO TEC Register, National Energy System Operator, publication of 23 Oct 2026. NESO Open Data Licence.