Blackpool BESS is a storage project of 25.3 MW in NESO's TEC Register of 23 Oct 2026, connecting at Bispham Primary 33kV Substation (NGET). Status: Built.
- Customer
- Conrad (Blackpool) Limited
- Connection site
- Bispham Primary 33kV Substation
- Transmission owner
- NGET
- Technology
- Storage
- Capacity (TEC)
- 25.3 MW
- Agreement
- Embedded
- Status
- Built
- NESO project number
- PRO-003080
Source
- NESO TEC Register, National Energy System Operator, publication of 23 Oct 2026. NESO Open Data Licence.