Bishopbriggs 500MW BESS

Bishopbriggs 500MW BESS is a demand, storage project of 500 MW in NESO's TEC Register of 23 Oct 2026, connecting at Bishopbriggs BESS 400/275kV Substation (SPT). Status: Scoping.

Customer
GPC Project 16 Ltd
Connection site
Bishopbriggs BESS 400/275kV Substation
Transmission owner
SPT
Technology
Demand, Storage
Capacity (TEC)
500 MW
Agreement
Direct Connection
Status
Scoping
MW effective from
28 May 2029