Bernicia Energy Park

Bernicia Energy Park is a storage, solar project of 350 MW in NESO's TEC Register of 23 Oct 2026, connecting at Stella West 400kV Substation (NGET). Status: Scoping. Gate 1.

Customer
BAYWA R.E. UK LIMITED
Connection site
Stella West 400kV Substation
Transmission owner
NGET
Technology
Storage, Solar
Capacity (TEC)
350 MW
Agreement
Direct Connection
Gate
Gate 1
Status
Scoping
MW effective from
30 Oct 2035
NESO project number
PRO-004541