Grid GuardianOpen the evidence in the app

Bendle Farm 2.0

Bendle Farm 2.0 is a storage project of 228 MW in NESO's TEC Register of 23 Oct 2026, connecting at BENDLE FARM 2.0 132KV SUBSTATION (SPT). Status: Scoping. Gate 1.

Customer
Balance Power Projects Limited
Connection site
BENDLE FARM 2.0 132KV SUBSTATION
Transmission owner
SPT
Technology
Storage
Capacity (TEC)
228 MW
Agreement
Direct Connection
Gate
Gate 1
Status
Scoping
MW effective from
31 Oct 2031
NESO project number
PRO-002700

Source