Bellrock Offshore Wind Farm

Bellrock Offshore Wind Farm is a offshore wind project of 1,200–1,800 MW in NESO's TEC Register of 23 Oct 2026, connecting at Hurlie 400kV substation (SHET). Status: Scoping.

Customer
Bellrock Offshore Wind Farm Limited
Connection site
Hurlie 400kV substation
Transmission owner
SHET
Technology
Offshore wind
Capacity (TEC)
1,200–1,800 MW
Agreement
Direct Connection
Status
Scoping
MW effective from
31 Oct 2032, 31 Oct 2035
NESO project number
PRO-001496-1, PRO-001496-2

Also at Hurlie 400kV substation

ProjectTechnologyMW
Bowdun (ex Cluaran Deas Ear) Offshore Wind FarmOffshore wind1,008
Cerulean Winds INTOG 1Demand, Offshore wind600