Grid GuardianOpen the evidence in the app

Beaw Field Wind Farm

Beaw Field Wind Farm is a onshore wind project of 102 MW in NESO's TEC Register of 23 Oct 2026, connecting at Beaw Field 132/33kV Substation (SHET). Status: Consents Approved.

Customer
BEAW FIELD SHETLAND LIMITED
Connection site
Beaw Field 132/33kV Substation
Transmission owner
SHET
Technology
Onshore wind
Capacity (TEC)
102 MW
Agreement
Direct Connection
Status
Consents Approved
MW effective from
29 Oct 2032
NESO project number
PRO-000026

Source