Bankside BESS
Bankside BESS is a storage project of 43 MW in NESO's TEC Register of 23 Oct 2026, connecting at Bainsford 132/33kV (SPT). Status: Under Construction/Commissioning. Gate 2.
- Customer
- FALKIRK POWER LTD
- Connection site
- Bainsford 132/33kV
- Transmission owner
- SPT
- Technology
- Storage
- Capacity (TEC)
- 43 MW
- Agreement
- Embedded
- Gate
- Gate 2
- Status
- Under Construction/Commissioning
- MW effective from
- 24 Nov 2025
- NESO project number
- PRO-002151