Baillie Greener Grid Park

Baillie Greener Grid Park is a storage, reactive compensation project of 48 MW in NESO's TEC Register of 23 Oct 2026, connecting at Baillie 275KV Substation (SHET). Status: Scoping. Gate 1.

Customer
Statkraft UK Ltd
Connection site
Baillie 275KV Substation
Transmission owner
SHET
Technology
Storage, Reactive Compensation
Capacity (TEC)
48 MW
Agreement
Direct Connection
Gate
Gate 1
Status
Scoping
MW effective from
30 Sept 2030
NESO project number
PRO-001701