Baillie Greener Grid Park
Baillie Greener Grid Park is a storage, reactive compensation project of 48 MW in NESO's TEC Register of 23 Oct 2026, connecting at Baillie 275KV Substation (SHET). Status: Scoping. Gate 1.
- Customer
- Statkraft UK Ltd
- Connection site
- Baillie 275KV Substation
- Transmission owner
- SHET
- Technology
- Storage, Reactive Compensation
- Capacity (TEC)
- 48 MW
- Agreement
- Direct Connection
- Gate
- Gate 1
- Status
- Scoping
- MW effective from
- 30 Sept 2030
- NESO project number
- PRO-001701
Source
- NESO TEC Register, National Energy System Operator, publication of 23 Oct 2026. NESO Open Data Licence.