Grid GuardianOpen the evidence in the app

Ashbrook Lane BESS

Ashbrook Lane BESS is a storage project of 249.9 MW in NESO's TEC Register of 23 Oct 2026, connecting at WEST ANGLIA CONNECTION NODE B 400KV SUBSTATION (NGET). Status: Scoping. Gate 1.

Customer
Downing Renewable Developments LLP
Connection site
WEST ANGLIA CONNECTION NODE B 400KV SUBSTATION
Transmission owner
NGET
Technology
Storage
Capacity (TEC)
249.9 MW
Agreement
Direct Connection
Gate
Gate 1
Status
Scoping
MW effective from
31 Oct 2034
NESO project number
PRO-003534

Also at WEST ANGLIA CONNECTION NODE B 400KV SUBSTATION

ProjectTechnologyMW
Wymondley FarmDemand, Storage, Solar1,000

Source