Grid GuardianOpen the evidence in the app

Arbroath Battery Substation

Arbroath Battery Substation is a storage project of 35 MW in NESO's TEC Register of 23 Oct 2026, connecting at Arbroath GSP (SHET). Status: Consents Approved.

Customer
ARBROATH LIMITED
Connection site
Arbroath GSP
Transmission owner
SHET
Technology
Storage
Capacity (TEC)
35 MW
Agreement
Embedded
Status
Consents Approved
MW effective from
21 Feb 2022
NESO project number
PRO-000950

Also at Arbroath GSP

ProjectTechnologyMW
CraigendSolar49.9
LocharberStorage, Solar50

Source