Alcemi Ridham Docks BESF

Alcemi Ridham Docks BESF is a storage project of 280 MW in NESO's TEC Register of 23 Oct 2026, connecting at North Kent Connection Node A 400kV Substation (NGET). Status: Scoping. Gate 1.

Customer
Alcemi Storage Developments 23 Ltd
Connection site
North Kent Connection Node A 400kV Substation
Transmission owner
NGET
Technology
Storage
Capacity (TEC)
280 MW
Agreement
Direct Connection
Gate
Gate 1
Status
Scoping
MW effective from
31 Oct 2033
NESO project number
PRO-003211

Also at North Kent Connection Node A 400kV Substation

ProjectTechnologyMW
NatPower-Medway Energy ParkStorage1,000