Al Boum Photo (Norton) is a storage project of 275 MW in NESO's TEC Register of 23 Oct 2026, connecting at Norton 400kV Substation (NGET). Status: Consents Approved.
- Customer
- AL BOUM PHOTO LTD
- Connection site
- Norton 400kV Substation
- Transmission owner
- NGET
- Technology
- Storage
- Capacity (TEC)
- 275 MW
- Agreement
- Direct Connection
- Status
- Consents Approved
- MW effective from
- 31 Oct 2031
- NESO project number
- PRO-001651
Also at Norton 400kV Substation
| Project | Technology | MW |
|---|---|---|
| Hill House Farm Solar and Storage | Storage, Solar | 99.9 |
| Norton | Storage | 57 |
| Norton PV and BESS | Storage, Solar | 40.9 |
| Norton Solar Farm | Solar | 180 |
Source
- NESO TEC Register, National Energy System Operator, publication of 23 Oct 2026. NESO Open Data Licence.