Grid GuardianOpen the evidence in the app

AGS Calderside Battery Energy Storage System

AGS Calderside Battery Energy Storage System is a storage project of 300–500 MW in NESO's TEC Register of 23 Oct 2026, connecting at AGS CALDERSIDE 275KV SUBSTATION (SPT). Status: Scoping. Gate 1.

Customer
Advance Grid Solutions Limited
Connection site
AGS CALDERSIDE 275KV SUBSTATION
Transmission owner
SPT
Technology
Storage
Capacity (TEC)
300–500 MW
Agreement
Direct Connection
Gate
Gate 1
Status
Scoping
MW effective from
31 Oct 2029, 31 Oct 2033
NESO project number
PRO-002752-1, PRO-002752-2

Source