Abedare
Abedare is a gas project of 10 MW in NESO's TEC Register of 23 Oct 2026, connecting at Upperboat 132kV Substation (NGET). Status: Built.
- Customer
- UK POWER RESERVE LIMITED
- Connection site
- Upperboat 132kV Substation
- Transmission owner
- NGET
- Technology
- Gas
- Capacity (TEC)
- 10 MW
- Agreement
- Embedded
- Status
- Built
- NESO project number
- PRO-000001
Also at Upperboat 132kV Substation
| Project | Technology | MW |
|---|---|---|
| Dowlais | Thermal | 21 |
Source
- NESO TEC Register, National Energy System Operator, publication of 23 Oct 2026. NESO Open Data Licence.