17 Acres and BESS
17 Acres and BESS is a storage project of 95.76 MW in NESO's TEC Register of 23 Oct 2026, connecting at 17 ACRES BESS 275KV SUBSTATION (SHET). Status: Scoping. Gate 1.
- Customer
- AEUK BATTERY PROJECT II LTD
- Connection site
- 17 ACRES BESS 275KV SUBSTATION
- Transmission owner
- SHET
- Technology
- Storage
- Capacity (TEC)
- 95.76 MW
- Agreement
- Direct Connection
- Gate
- Gate 1
- Status
- Scoping
- MW effective from
- 30 Jun 2032
- NESO project number
- PRO-004392
Source